What we were asked to do
Greenpipe was commissioned to rapidly implement an efficient drainage solution within the construction site area of the commercial port of Augusta, specifically in the area highlighted in green in Figure 1.
For the client, both the functionality of the system—to ensure the yard remained well-drained even during heavy rainfall—and load resistance were critical to guarantee suitability for vehicles during maneuvers involving very heavy loads (F900).

The context
The Port of Augusta, in the province of Syracuse, is a major commercial hub and military base, thanks to the unique characteristics of its seabed which allow ships of all sizes to dock with relative ease. Its location at the center of the Mediterranean has always made it ideal as an industrial port and a hub for international transit.
The Port System Authority, via memorandum prot. no. 5436/UFF.TEC dated 2017-09-05, expressed the need to carry out extraordinary maintenance on the breakwater in front of the Port of Augusta to ensure the safety of navigation within the roadstead.
The project
- 158,576.31 m³ of 60-ton cubic artificial blocks
- 2,709.53 m³ of 43-ton artificial blocks
- 670.20 tons of natural rocks
- Quarry aggregates or gravel: 193,543.00 tons
- Sand: 90,320.06 tons
- Cement: 48,385.75 tons
- Water: 19,354,299.59 liters
The Greenpipe Solution: BIG I nS 300 H520 - F900
We conducted a hydraulic study of the system, selecting not only the best section to minimize the width of the grate but also proposing the correct number of outlets and positioning them appropriately using the hydraulic calculation software developed by Greenpipe.
By inputting the hydrological data provided by the client, the characteristics of the yard (surface area, slopes, type of paving, runoff types) and setting the maximum expected filling level of the channel, the ideal solution was obtained through iteration. This verified the system while ensuring correct shear stress at the bottom—meaning a water velocity that was neither too fast (which would cause outlet malfunction) nor too slow (which would impair the channel’s self-cleaning capacity).

The contractor awarded the project, in agreement with the works management, opted for our Big I nS reinforced cast concrete channel Type I F900 with a cast iron profile to protect the upper edge, featuring elements 3.00 meters in length. Specifically, the chosen BIG I nS model was the 300 H520 (internal section 300×400 mm) with a “Z”-shaped cast iron profile.
This is the best possible solution because:
- in the event of heavy loads on the structure, the “Z” profile ensures total protection of the concrete against wear and impact;
- the self-supporting channels (Type I), requiring no additional concrete haunching, allowed for the immediate operation of the yard, simplifying the management of all other site activities;
- the installation of the channel was accelerated thanks to the length of the units (3 meters);
- the lateral outlets created during production facilitated the work on site.
Project figures
189 meters of channels with 378 grates were delivered to the site within two weeks of the request
for a total of:
